DPM 2012 SP1 + Exchange 2013 log truncation question

$
0
0

I have the following setup.


At production site,

DBSvr01 holds databases DB01, DB02

DBSvr02 holds databases DB02, DB03

DBSvr03 holds databases DB03, DB01


At DR site,

DBSvr04  holds databases DB01, DB02, DB03

I have a DPM server installed at DR site and I am going to setup a protection for all DBs in server DBSvr04. The protection will be set as "Full backup".

Question:

I suppose only the log in server DBSvr04 (but not the other DB servers) will be truncated. Am I correct?

Best regards,

Joseph